SouthPark Phase 1 Underway

July 30, 2025

SouthPark Pastor Nic Schrieber shares an update about the Phase 1 construction at New City SouthPark. Check out these spaces that are being renovated to help kids and students find and follow Jesus! Below are some progress updates and photos of the process!

What’s Been Happening (July):

  • Construction fencing is up and demolition is complete in the east and west wings of the worship center.
  • Temporary walls were built to keep the sanctuary safely accessible on Sundays.
  • The old entry canopy on the west side was removed.
  • Crews started laying out the walls for the new classrooms and began work on underground plumbing and new ductwork.

What’s Coming Up (August):

  • Overhead mechanical, electrical, and plumbing systems will go in.
  • Underground plumbing will be completed and the floors poured back.
  • Framing will begin for interior walls and the new west entry.

Other Here, Near, & Far updates

A God-sized vision that will transform how we help people find & follow Jesus Here, Near, & Far.
A God-sized vision that will transform how we help people find & follow Jesus Here, Near, & Far.
A God-sized vision that will transform how we help people find & follow Jesus Here, Near, & Far.
A God-sized vision that will transform how we help people find & follow Jesus Here, Near, & Far.

Join us in our vision

Make a big faith commitment and be part of transforming lives